668 Troubled Housing Projects in Peninsular Malaysia (2026): How to Check a Project Before You Buy

Quick answer

KPKT says Peninsular Malaysia had 668 problem private housing projects as at 31 August 2026, involving about 108,760 homes: 128 delayed, 278 sick, 99 licensed abandoned and 163 unlicensed abandoned. The good news is that KPKT says it has rescued 1,726 troubled projects (199,643 units) since 2023 and aims for zero sick and abandoned projects by 2030. For buyers, the lesson is simple: check the developer and the project’s real progress on TEDUH and on site before you pay a booking fee, and choose a payment structure you can live with if work slows.

Policy watch · October 2026

Most projects get built. Check yours anyway.

668Delayed, sick or abandoned private projects in Peninsular Malaysia, as at 31 Aug 2026 (KPKT)
108,760Homes inside those 668 projects
1,726Troubled projects KPKT says were rehabilitated since 2023, covering 199,643 units
Research by DMS Jason Chan · Sources listed at the end of this article

What KPKT reported this month

In mid-October, Housing Minister Nga Kor Ming told the Dewan Rakyat that 1,726 private housing projects worth about RM158 billion in gross development value had been restored since the sick and abandoned projects task force was set up in 2023. A few days later, Deputy Minister Datuk Aiman Athirah Sabu gave the other side of the ledger: the projects that are still in trouble.

Status (Peninsular Malaysia, 31 Aug 2026)ProjectsHomesGDV
Delayed12829,048RM24.39 billion
Sick27840,818RM38.02 billion
Abandoned (licensed developer)9928,289RM15.40 billion
Abandoned (unlicensed)16310,605Not stated
Total668108,760

Kuala Lumpur alone had 7 abandoned and 12 sick private projects at the end of August, according to Bernama. One well-known rescue, Residensi Hektar Gombak, was reported at 92.67% physical progress, with completion expected in the first quarter of 2027 and vacant possession scheduled for the second quarter.

Delayed, sick, abandoned: what the labels mean for you

KPKT’s categories describe how far a project has fallen behind its planned schedule. A delayed project is behind but still moving. A sick project is seriously behind, often with cash-flow, contractor or approval problems. An abandoned project has effectively stopped. The unlicensed group is the most worrying for buyers, because those projects were sold without a proper housing developer’s licence, which means far fewer protections.

Put in perspective, most projects in Malaysia do get completed. But if you are one of the families in a sick project, you may be paying loan interest and rent at the same time, with no keys in sight. That is why a 30-minute check before booking is worth it.

Facade of Levia Residence, Cheras
Track record and visible progress matter. Levia Residence, Cheras topped out in March 2026, with completion targeted for 2027.

A seven-step check before you pay a booking fee

  1. Search TEDUH. KPKT’s TEDUH portal lets the public look up housing projects, their construction status and the developer behind them.
  2. Ask for the licence and the advertising and sales permit. A licensed project must display them. No permit, no deal.
  3. Check the developer’s history. Look at its completed projects, whether they were handed over on time, and how owners describe the handover.
  4. Visit the site on a weekday. Count the workers and cranes. Compare what you see with the stage the developer claims.
  5. Match progress with the payment schedule. In the standard SPA for strata homes, you pay in stages tied to construction milestones. Ask which stage has been certified.
  6. Ask your bank. Banks review projects before financing them. If panel banks are reluctant, find out why.
  7. Read the booking form. Know the refund terms. KPKT is studying a new option-to-purchase system for booking fees, but it is not in force yet.

Off-plan or completed: how much risk do you want?

This news is also a reason to consider a completed or nearly completed home. You pay a little more today, but you can see exactly what you are buying, and there is no construction risk.

OptionConstruction riskWhat you gainWhat to check
Early off-plan launchHighestEarly-bird pricing, progressive payments, newest designDeveloper track record, TEDUH status, bank financing
Topped-out projectLowerVisible building, shorter waitRemaining works, CCC timeline, defects history
Completed new or subsaleNoneSee the actual unit, move in or rent out quicklyPrice vs recent transactions, maintenance, management

I compared these routes in more detail in completed vs new launch condo in KL and off-plan vs completed in Shah Alam. A completed example in our listings is Axis Crown, Ampang, right beside the LRT.

Property contract and land title documents on a desk, illustrative
Read the SPA payment schedule before you sign. It tells you exactly what you pay at each construction stage. (Illustrative photo)

If your project is already in trouble

  • Do not stop paying your loan without advice. Missed payments hurt your credit record, which you will need later.
  • Join or form a buyers’ group and keep every receipt, letter and progress report.
  • Contact KPKT and your bank early. KPKT says it is strengthening early intervention, closer monitoring and site visits; of 33 delayed and sick projects it visited, 23 have since obtained their CCC.
  • Speak to a lawyer about late-delivery compensation and the Tribunal for Homebuyer Claims. Check the current claim limit before filing.

💡 My practical view: 668 projects sounds frightening, but it is a small share of what gets built. The buyers who get hurt usually skipped the basic checks or bought from unlicensed sellers because the price looked too good. With loan approvals tighter this year, also get a pre-assessment first; see how to get your home loan approved in 2026. First-time buyers can start with our first home buyer guide.

Frequently asked questions

How many sick and abandoned housing projects are there in Malaysia in 2026?
KPKT reported 668 problem private housing projects in Peninsular Malaysia as at 31 August 2026: 128 delayed, 278 sick, 99 licensed abandoned and 163 unlicensed abandoned projects, involving about 108,760 homes. Since 2023, KPKT says 1,726 troubled projects with 199,643 units have been rehabilitated.
How do I check if a housing project is sick or abandoned?
Search the project and developer on KPKT’s TEDUH portal (teduh.kpkt.gov.my), which shows construction status, the developer and the agencies involved. Also ask for the developer’s licence and advertising and sales permit, visit the site, compare progress with the payment schedule in the SPA, and ask your bank whether it is financing the project.
What happens to my loan if my project is abandoned?
Under a typical progressive-release loan, you pay interest only on the amount the bank has released, but you still have to keep paying it even if work stops. That is why it matters to check a project before you sign. If a project is in trouble, contact KPKT, your bank and a lawyer early, and keep all receipts and correspondence.

Want a second pair of eyes on a project?

WhatsApp DMS Team before you pay a booking fee. We will help you check the developer, the project status and your loan eligibility, free of charge.

Jason Chan (DMS Jason Chan), REN 78007

About the author: Jason Chan (DMS Jason Chan)

Jason is a registered real estate negotiator (REN 78007) and founder of DMS Team, a property consultancy registered under EUM Realty Sdn Bhd [E(1)1708] with consultants across Kuala Lumpur and Johor Bahru. He researches and reviews every market analysis published on dms-team.com.

More about Jason and DMS Team · Facebook · YouTube

This article is general information as at 26 October 2026, written from an agent’s practical perspective. It is not legal or financial advice. Figures are as reported from KPKT parliamentary and ministry statements and may be revised. Always confirm a project’s status with KPKT, your lawyer and your bank before committing.

Sources: EdgeProp: KPKT says 1,726 troubled housing projects rehabilitated (19 October 2026); Bernama: 1,726 projek perumahan swasta berjaya dipulihkan (14 October 2026); EdgeProp Daily Digest, 19 October 2026; MyGOV: Portal TEDUH; KPKT TEDUH portal.

Last updated 26 October 2026 · DMS Jason Chan, REN 78007

Leave a Comment

Your email address will not be published. Required fields are marked *

Follow DMS Team: Facebook · Instagram · TikTok · Xiaohongshu · YouTube · LinkedIn
Scroll to Top